EEDC Explains Why its Customers Under Ezillo and Eha-Amufu 33KV Feeders are Out of Supply

images (4)
Some customers of Enugu Electricity Distribution Company (EEDC) under Nsukka and Abakaliki Districts being serviced by the Ezillo and Eha-Amufu 33KV Feeders have been out of supply for some time now as a result of a fire outbreak that occurred at the Transmission Company of Nigeria (TCN) Station, Nkalagu on Saturday, 2nd December, 2017 at 14:25hrs.
As a result of this development,  the T1A Power Transformer at the Station, belonging to TCN, which supplies power to the mentioned Feeders was severely burnt, thereby putting customers in the affected area out of supply.
However, as a palliative, EEDC is making alternative arrangement to provide supply to the affected customers. “While this may not be adequate due to some constraints, we appeal to our esteemed customers to kindly bear with us”.
We are sincerely sorry for the inconvenience this unfortunate incident will cause our esteemed customers, and assure them that normal supply will be restored as soon as the transformer is replaced.
Source: IWIN
(Visited 8 times, 1 visits today)