Total Blackout in Port Harcourt as Youths Shut Down Afam Transmission Station

blackout (1)

The Rivers State capital, Port Harcourt has been in total blackout for days.

This is because youths from Oyigbo Local Government area of the State shut down transmission of the Afam Power Plant.

The youths claimed that host communities do not pay for power, adding that they are entitled to free power supply.

Reacting to the protest, spokesman of the PHEDC, John Onyi said Oyigbo, the host community was disconnected because of their refusal to pay for supply.

Onyi said communities around Afam is owing PHEDC over five billion Naira just as he appealed to the youths to vacate the Afam Transmission Station to allow for the return of normal activities to the State.

Source: Daily Post
(Visited 37 times, 1 visits today)